The family wanted a bathroom an older parent could use safely for years, without it looking like a hospital. In a prewar co-op that means two jobs at once: the construction, and the building.
On the building side we worked through the co-op’s alteration agreement with the managing agent: scope of work, insurance certificates naming the co-op corporation and managing agent, the licenses for our plumber and electrician, and the work-hour and holiday rules. On the construction side, a prewar bathroom is slower than it looks.
What We Did
Prewar demolition
Layers of old tile on a thick mortar bed, metal lath and heavy plaster, carried out within building hours with the hallway and elevator protected. In a prewar co-op this takes days, not one afternoon.
Framing and floor corrected
With the walls open, the old studs were straightened and sistered, solid blocking went in at every grab bar location, and the floor was rebuilt flat and sound before any waterproofing.
Licensed plumbing and electrical
Our licensed master plumber reworked the supply and drain for the new shower and valve, coordinated with the super for the riser shutoff. A licensed electrician wired the lighting and a new exhaust fan.
Shower pan and waterproofing
A sloped shower pan and a full waterproofing membrane on the walls and floor. With an apartment below, this is the step that matters most.
Tile, fixtures and accessibility
Large-format marble-look porcelain walls, a hex mosaic floor and a recessed niche. A rain head plus a handheld on a slide bar, a fold-down teak seat, brushed nickel ADA grab bars, a sliding glass door and a floating wood-tone vanity.
Before and After
What This Job Teaches About Co-op Bathrooms
- Budget time for the board. About three weeks of paperwork came before the first day of demo.
- Licensed trades are part of the base scope. The co-op required a licensed plumber and electrician, so they belong in the first price, not a change order.
- Prewar walls hide work. Expect framing and floor correction once the old tile and plaster come off.
- Lock the fixtures before signing. The shower pan, valve system, toilet and accessible hardware change the rough-in, so they are chosen first.
More on the process and cost: co-op and condo bathroom renovation, and our guide to ADA and accessible bathrooms in NYC.
Related
Canaj Management is a Licensed NYC Contractor, DCWP Home Improvement Contractor #2134434, fully insured, based at 72-20 Forest Ave, Ste 1B, Ridgewood, NY 11385. We build co-op, condo and private-home bathrooms across NYC, specializing in Brooklyn and Queens.
Call (718) 200-4898 or email [email protected].