The finish is the part everyone sees, and structurally the part that matters least. What decides whether a stucco wall lasts is underneath it: lath fastened to something solid, a scratch coat that keys the next one, and a brown coat floated flat and given time to cure.

A smooth finish is the least forgiving texture there is. Any wave left in the brown coat shows the first time afternoon sun rakes across the wall, so there is no hiding a rushed base. That is the standard we built this wall to.

LocationSt Marks Ave, Crown Heights, Brooklyn
BuildingRow house, four-story rear elevation and extension
SystemLath, scratch, brown, Parex acrylic smooth
AccessCompany-owned scaffold, erected by our crew
Also on this jobParty wall coating, patio, basement windows, cedar yard
TradesStucco, masonry prep, windows, concrete

What Was Wrong

What We Did

Step 1

Scaffold up, property protected

Our own scaffold frames, guardrails and OSHA-compliant planking, erected by our crew. Windows, the yard and the neighbor's side sheeted before anything was mixed.

Step 2

Galvanized lath and beads

Galvanized lath fastened through to solid masonry, with corner and casing beads so every edge stays crisp.

Step 3

Scratch coat

Pressed hard into the lath and combed with horizontal grooves so the next coat has something to key into.

Step 4

Brown coat, floated flat

Built up and floated flat and true across both walls, then given time to cure. This coat decides whether the finished wall reads straight.

Step 5

Parex acrylic smooth finish

Applied only once the base had fully cured. From the same scaffold we coated the neighbor's party wall, fitted larger basement windows and poured a new concrete patio.

Before and After

Before and after of a St Marks Ave rear facade in Crown Heights: exposed brick and construction debris on the left, the same wall in white Parex acrylic smooth stucco with black windows and a new lawn on the right
Rear facade. Exposed brick to smooth stucco, black windows, new lawn.
Company-owned scaffolding across a four-story rear facade on St Marks Ave in Crown Heights, with crew in hard hats and harnesses and windows masked
Our scaffold. Frames, rails and planking we own, erected by our crew.
Scratch coat applied over galvanized lath on a Crown Heights rear facade, crew working at the garden level
1. Scratch coat pressed into the lath and combed.
Brown coat floated flat across a Crown Heights rear extension with scaffolding and planking in place
2. Brown coat floated flat and left to cure.
Crew member on scaffold planking applying Parex acrylic smooth finish to a Crown Heights rear facade
3. Parex finish going on over the cured base.
Finished white stucco rear facade and extension on St Marks Ave in Crown Heights with black windows and new lawn
4. Finished scaffold struck, yard rebuilt.

The yard behind this wall was rebuilt on the same job: see the cedar fence and backyard project →

Related

Canaj Management is a Licensed NYC Contractor, DCWP Home Improvement Contractor #2134434, fully insured, based at 72-20 Forest Ave, Ste 1B, Ridgewood, NY 11385. We build and repair exterior stucco across NYC, specializing in Brooklyn and Queens.

Call (718) 200-4898 or email [email protected].